"Simon Riggs" <simon@2ndquadrant.com> writes:
> [ expecting to finish PITR by early June ]
> Is this all still OK for 7.5? (My attempts at cataloguing changes has
> fallen by the wayside in concentrating on the more important task of
> PITR.) Do we have a planned freeze month yet?
There's not really a plan at the moment, but I had June in the back of
my head as a good time; it looks to me like the Windows port will be
stable enough for beta in another month or two, and it'd be good if
PITR were ready to go by then.
Is your timeline based on the assumption of doing all the work yourself?
If so, how about farming out some of it? I'd be willing to contribute
some effort to PITR. (It's been made clear to me that Red Hat really
wants PITR in 7.5 ;-))
regards, tom lane