On Tuesday 26 February 2008 5:32 pm, Bruno Baguette wrote:
> Hello !
>
> I have a week number (ISO 8601) and a year, based on theses values, I
> would like to get the first and the last dates of that week.
>
> How I can do that ?
>
> The only solution is doing a big generate_series to build a subset that
> contains the week of all the dates between the 01/01 || year and the
> 31/12 || year. But I find that solution quite dirty and ressources
> consumming.
>
> Is there a cleanest way to do that ?
>
> Many thanks in advance !
>
> Regards,
This will get you to the Monday of the week .
select to_date('9 08','IW YY');
to_date
------------
2008-02-25
(1 row)
Where 9 is the ISO week number and 08 is the year. See below for more details:
http://www.postgresql.org/docs/8.2/interactive/functions-formatting.html
--