On Thu, May 16, 2013 at 11:04 AM, Oscar Calderon <ocalderon@solucionesaplicativas.com> wrote:
Hi everybody, this is my first message in this list. The company where i work is bringing maintenance service of PostgreSQL to another company, and currently they have installed PostgreSQL 9.1.1, and they want to move to 9.3 version when it will come out. So, because the difference of versions, and because it was installed by compiling it (using source code), and because the 9.1.1 installation is in a different directory than the default, they decided to replace 9.1.1 version with 9.3 (no upgrade, but replace it). 

Currently, they only have one database in production of 2.2 GB with some procedures and triggers. So, my plan to execute this database installation is the next:

  1. Install PostgreSQL 9.3 from postgresql repository (yum.postgresql.org) with a different port to avoid interrupt the production PostgreSQL instance operation
  2. Tune the database parameters in postgresql.conf, also create the same rules in pg_hba as the production instance, configure log and so on.
  3. At the end of the operations day, create a backup of the production database and then restore it into the new instance
  4. Test the new instance with the PHP applications that use it and verify that all is in order
  5. Stop the old instance and change the port to another port, then change the port of the new instance to 5432 in order to avoid change the network configuration, permissions and so on.

But really is the first time that i do that, so i don't know if i'm missing something or there's something wrong about i'm planning to do, so i will appreciate very much if you can guide me about what steps i have to do exactly and considerations during this process.


I would expand step 4 into a much longer period.  Say, do steps 1..3 (you don't even have to stop your services ... do it during a low-traffic period), then spend a few days on step 4 to ensure that all of your applications work and that you don't have any queries that have problems.  Unless your application is really simple, it will take more than an hour or two to ensure that the migration will go well.

Once you're convinced that everything will work, discard the new 9.3 database and start over again at step 1, and this time complete through step 5.

Craig


Regards.

***************************
Oscar Calderon
Analista de Sistemas
Soluciones Aplicativas S.A. de C.V.
www.solucionesaplicativas.com
Cel. (503) 7741 7850

pgsql-admin by date:

Previous
From: "Gilberto Castillo"
Date:
Subject: Re: Migration of server
Next
From: Alejandro Brust
Date:
Subject: Re: Migration of server