On Thu, Oct 2, 2008 at 4:21 PM, <susan.williams@us.michelin.com> wrote:
>
> I am experiencing an issue with pgadmin 1.8.4 (Windows). The issue is with
> the pgagent job scheduler. I am able to create new jobs and steps.
> However, I am unable to create a new schedule. I am also unable to edit /
> change a schedule that currently exist. The schedule window informs me that
> I must enter a start date. I do this and it still does not recognize that
> it has a date and will not activate the OK button even though there is a
> visible date in the field. I have used the drop down in the field as well
> as tried typing in the date with no luck. One of my co-workers is having
> the same problem and is running the same version (1.8.4 - however he is
> running linux ). The other co-worker is not having this problem and is
> running version 1.8.0 (linux ). I tried to go back to 1.8.0(Windows); but,
> was still unable to create a new schedule. Thanks for your assistance
> regarding this issue.
>
It works for me on OS X, though somewhat annoyingly it seems to be
using MM/DD/YYYY. If you modify another control after selecting the
date (ie. add a comment), does that allow it to recognise there's a
date there?
--
Dave Page
EnterpriseDB UK: http://www.enterprisedb.com