I brought down the master then the slave and upgraded both. Then I did the
rsync and brought both up.. This worked. However with the database being
very large it took quite a while. It seemed rsync had to make a lot of
changes.. this surprised me. I thought they would be almost identical.
But in the end it did work. just took longer than I had hoped.
We will soon be tripling the size of our database as we move oracle data
in.. so this process may not be so feasible next time.
--
View this message in context:
http://postgresql.1045698.n5.nabble.com/How-to-upgrade-from-9-1-to-9-2-with-replication-tp5728941p5729618.html
Sent from the PostgreSQL - performance mailing list archive at Nabble.com.